Deborah Lazar/Special to The Commons
U.S. District Court Judge J. Garvan Murtha on Monday issued an injunction that will permit Vermont Yankee to operate during the appeals process of the Entergy v. Vermont lawsuit.
With additional reporting from Alan Panebaker of VTDigger.org. Updated at 5 p.m. on Tuesday, March 19.
This story has not yet appeared in print.
BRATTLEBORO—The owner of the Vermont Yankee nuclear power plant won a crucial victory in federal court on Monday when U.S. District Judge J. Garvan Murtha issued an injunction that prevents the state of Vermont from closing the nuclear plant when VY’s current state permit expires on March 21.
Murtha granted Entergy’s request regarding spent fuel storage, saying that the state cannot shut the plant “pending the appeal of the Court’s final judgment and merits decision to the Second Circuit, from addressing the storage of spent fuel” under Vermont statutes.
He further prevented the state “from bringing an enforcement action, or taking other action [...] to compel Vermont Yankee to shut down because the ‘cumulative total of spent fuel stored at Vermont Yankee’ exceeds ‘the amount derived from the operation of the facility up to, but not beyond, March 21, 2012.’”
Murtha wrote that, based on Vermont law, the state would allow the plant to operate past that date while the CPG process continues. Thus, he wrote that the court “does not see the need to consider at this time Entergy’s request for an injunction pending appeal.”
Despite a ruling by Murtha in January that found that federal law superseded two Vermont laws, attorneys for Entergy had expressed concerns that the Vermont Public Service Board (PSB) would not allow Vermont Yankee to continue operating without the state Certificate of Public Good (CPG) that the plant needs to function legally.
The company asked Murtha for assurance that the plant could continue operating during the state’s appeal of his January ruling that the federal Atomic Energy Act pre-empted two state laws that required legislative approval to store spent nuclear fuel at VY after March 21, and for continued operation after that date.
However, Murtha’s January ruling left the PSB’s discretion over the CPG intact. That ruling is currently being appealed by the state to the Second Circuit of the U.S. Court of Appeals in New York City.
The plant got a 20-year extension from the U.S. Nuclear Regulatory Commission last March.
When the PSB reopened the VY docket after Murtha’s January ruling, it asked whether the plant could continue to operate. Entergy then fired off an immediate request to the federal court asking it to let the plant operate after March 21.
At the same time that Murtha was issuing his ruling, the PSB issued an order on Monday regarding Entergy’s request that it be allowed to continue operating VY and to keep storing spent nuclear fuel from the plant while its CPG petition is pending.
Entergy’s request for the PSB to issue a declaratory ruling on its request was denied.
In the spent-fuel-storage request, the PSB wrote that state statute “does not provide authority for Vermont Yankee to continue operating, and storing spent fuel derived from such operation, while Entergy’s VY petition for a new or amended CPG remains pending.”
The PSB also stated it did not have authority to act on Entergy’s contention that the Legislature does not need to approve spent fuel storage at VY after March 21.
“In rendering today’s decision, we have applied the relevant provisions of state law that have not been pre-empted or enjoined by the federal District Court,” the PSB wrote.
“We are mindful of the [Department of Public Service’s] contention that the District Court’s decision serves to enjoin the Board from enforcing orders that would require cessation of operations at Vermont Yankee.
“Our Order today does not have that effect. Today’s order does not purport nor is intended to require that Entergy VY cease operations.”
Meanwhile, the state has also asserted to the PSB that Entergy must meet its obligation to fund the Clean Energy Development Fund.
Editor’s note: Our terms of service require you to use your real names. We will remove anonymous or pseudonymous comments that come to our attention. We rely on our readers’ personal integrity to stand behind what they say; please do not write anything to someone that you wouldn’t say to his or her face without your needing to wear a ski mask while saying it. Thanks for doing your part to make your responses forceful, thoughtful, provocative, and civil. We also consider your comments for the letters column in the print newspaper.


Obituaries/Births/News of Windham County people
—

We make our news available at no cost, but that doesn't mean it comes free. Reader memberships and donations make a huge difference and help all Vermont Independent Media programs, including The Commons and the Media Mentoring Project

Information and rates about advertising in The Commons
Information and rates about advertising on Commonsnews.org

The Commons, Commonsnews.org, and the Media Mentoring Project are projects of Vermont Independent Media, a nonprofit source of news and media education in southern Vermont.

Vermont Independent Media
139 Main St., #604
Brattleboro, VT 05301
802-246-6397
info@commonsnews.org
—
General contacts
Newsroom/submit announcements:
news@commonsnews.org
Advertising inquiries:
ads@commonsnews.org
Comments (2)
Big Corporations Win Again!
Add Comment