Entergy seeks to sell VY to deconstruction firm
The current dry cask storage area at the Vermont Yankee nuclear plant in Vernon.
News

Entergy seeks to sell VY to deconstruction firm

Sale to NorthStar — subject to state, federal approval — would accelerate decommissioning process

VERNON — Entergy has agreed to sell Vermont Yankee to a cleanup contractor, paving the way for decommissioning and site restoration to be completed by 2030 - 45 years sooner than had been planned.

The sale of the shut-down Vernon nuclear plant and all its assets - including the decommissioning trust fund, which held $574.9 million at last report - to New York-based NorthStar Group Services Inc. is expected to close by the end of 2018, administrators announced Nov. 8.

The deal is subject to approval by the Vermont Public Service Board and the federal Nuclear Regulatory Commission.

Simultaneously, Entergy announced that the plant's spent nuclear fuel may be moved into sealed dry casks by the end of 2018, two years sooner than expected. That will hasten additional layoffs.

But officials emphasized that the shortened schedules for fuel transfer and decommissioning mean that redevelopment of much of the Vermont Yankee site won't have to be postponed for generations.

Looking toward redevelopment

Bill Mohl, the president of Entergy Wholesale Commodities, said in a statement that “by accelerating decommissioning, we are fulfilling a commitment we made in 2013 to decommission Vermont Yankee as soon as reasonably possible.”

“Decommissioning and site restoration, drawing on NorthStar's expertise, will provide economic development for the region,” Mohl said.

NorthStar CEO Scott State underscored that point. While land used for fuel storage will remain off-limits until the federal government removes the radioactive material, Scott said his company's decommissioning work will ensure that “a majority of Vermont Yankee can be redeveloped to promote business for the region.”

Citing economic reasons, and after a long struggle with state officials and anti-nuclear activists, Entergy stopped power production at Vermont Yankee on Dec. 29, 2014. The plant had operated on the banks of the Connecticut River for 42 years.

And it was expected to be a long-term presence there: Rather than pursuing immediate decommissioning, Entergy opted for SAFSTOR, a period of dormancy under which radiological cleanup and site restoration can take up to 60 years.

Some have protested that the SAFSTOR timeline is too long. Vermont officials have lobbied the NRC to eliminate the SAFSTOR program, and U.S. Rep. Peter Welch, D-Vt., has raised questions about the impact of delayed decommissioning on a community like Vernon.

But the NRC has endorsed SAFTOR, and federal projections have shown that it could be 2075 before Vermont Yankee is fully decommissioned.

That's about to change dramatically, if all goes as Entergy plans in a deal that has been in the works for years. Before agreeing to sell Vermont Yankee to NorthStar, Mohl said, “we went through and evaluated a number of different entities to perform this work.”

“Obviously, this is something that is a very significant transaction,” Mohl said in an interview after the sale announcement. “We made sure to do our homework.”

Mutual benefits

By selling the plant and arranging for a faster cleanup, Entergy will be getting out from under the long-term financial uncertainties associated with putting off decommissioning until the 2060s and 2070s.

NorthStar, presumably, plans to turn a profit on the job. “They're able to minimize the range of [financial] risk,” Mohl said of NorthStar. “They believe that they can make this a profitable business.”

NorthStar, which specializes in projects like demolition, hazardous-materials abatement, and soil and mold remediation, initially is giving Entergy a “nominal cash consideration” to gain ownership of Vermont Yankee. Mohl said that amount is $1,000.

Also, Entergy is getting a promissory note equal to “the amount owed at the time of closing under a credit facility to finance Vermont Yankee's dry fuel storage costs,” the company's announcement said.

That number could be significant. Entergy has taken out a $143 million line of credit to cover the transfer of spent fuel to so-called “dry” storage.

Likely of much more interest to locals is NorthStar's accelerated cleanup schedule for Vermont Yankee.

The company is agreeing to start decontamination and dismantlement by 2021 and to complete decommissioning and site restoration nine years later, Entergy administrators said.

Partners in decommissioning

NorthStar is partnering with three other companies to tackle the job:

• Paris-based AREVA, which has 10,000 employees worldwide, touts extensive experience in all aspects of nuclear power generation. Entergy said AREVA will be responsible for reactor work and spent fuel management support at Yankee.

• Burns & McDonnell, a Kansas City, Missouri, company that describes itself as “a full-service engineering, architecture, construction, environmental, and consulting solutions firm,” will handle engineering and regulatory support in Vernon.

• Dallas-based Waste Control Specialists, which operates a radioactive waste disposal site in Texas, will be in charge of Vermont Yankee's “waste management, packaging, transportation, and disposal,” Entergy said.

Waste Control Specialists is among the entities that have applied to the NRC to build a new interim storage facility - also in Texas - that could hold spent nuclear fuel.

Regardless of the speed of decommissioning, the presence of spent fuel is a major obstacle to reusing the Vermont Yankee site. No one is sure how long spent fuel will remain there, and that's one reason the recent permitting process for a second spent fuel pad at Vermont Yankee was so contentious.

Current federal plans call for Vermont Yankee fuel removal to start in 2026 and end in 2052. But the federal government doesn't yet have a long-term storage site for any spent nuclear fuel, leaving some to wonder whether shuttered plants like Yankee will be saddled with the material for much longer.

Entergy said NorthStar will maintain Vermont Yankee's spent fuel storage facility until the Department of Energy eventually removes the material; then, the company will pursue NRC license termination and full site restoration.

Fast-tracking fuel transfer

Crews have begun building a second pad for fuel storage at Vermont Yankee, since the current pad cannot hold all the spent fuel that now is housed in a cooling pool inside the reactor building.

Florida-based Holtec International is handling all aspects of that fuel transfer, and that's where the other part of the Nov. 8 announcement comes in.

Entergy, which had promised to move all fuel into sealed casks by the end of 2020, now says Holtec has applied for NRC approval to finish the job by the end of 2018. That's faster than the normal cooling period for some of the plant's nuclear fuel, but officials say Holtec will argue that technology exists to do the job more quickly.

“We have worked with Holtec, and they now have the capability with their cask design to actually transfer that fuel sooner,” Mohl said. “We've spent a lot of time looking at this, and it's very safe to do so. It's prudent to move that fuel from the fuel pool to the pad.”

But if the NRC approves the faster fuel-transfer schedule, there will be implications for remaining Vermont Yankee employees.

Yankee has periodically shed staff, and the last major layoff happened in May. A plant that once employed more than 600 now has fewer than 100 workers, and only a handful of those will be needed once all fuel is inside dry casks.

It isn't clear whether NorthStar would keep any current employees after its purchase of Vermont Yankee.

Mohl said he expects that NorthStar would want to retain some of the plant staff's expertise, and he said those employees who lose their jobs will have opportunities to find positions at other Entergy facilities.

Regardless of the new owner's plans, the culmination of the Vermont Yankee sale - assuming all regulatory hurdles are cleared - will mark the official end of Entergy's 14-year role as a major employer in Windham County.

It's also a continuation of Entergy's oft-stated intention to shrink its Wholesale Commodities operation. Entergy also has announced plans to close its Pilgrim nuclear plant in Massachusetts in 2019, and the company is seeking to sell its FitzPatrick plant in upstate New York to Exelon Corp.

Mohl said the sale of Vermont Yankee to NorthStar has no connection to either the Pilgrim or FitzPatrick deals. But he noted that the deal “enables us to manage financial risk and reduce our company's merchant power footprint.”